SAP C_TPLM22_64 Exam Questions And Information – (Feb-2018 Dumps)

The vcebraindumps’s SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 Exam Dumps preparation package presented as the C_TPLM22_64 exam practice test software and PDF Q&A booklet. The booklet contains the most updated C_TPLM22_64 exam questions of SAP Project System with SAP ERP 6.0 EHP4 Project System with SAP ERP 6.0 EHP4 certification exam is very similar to the actual C_TPLM22_64 exam questions. Free demo and user-friendly interface of the software makes the C_TPLM22_64 exam preparation source amiable and reliable. MacAfee Secure payment method makes shopping of the products convenient and risk free.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks.
How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time?
Please choose the correct answer.
Response:

A. Safety measures
B. Status management
C. Claim management
D. Actions

Answer: C

Question: 22

Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?
Please choose the correct answer.
Response:

A. Overheads costing
B. Planned costing
C. Profitability costing
D. Activity based costing

Answer: D

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD